Skip to main content

​ ​

​

 

Electronic Theatre Controls Inc

Changing sACN Universe Priority Dynamically in Mosaic 2

I need to dynamically change the sACN universe priority of a universe within my Mosaic configuration. 

Explanation of Issue

In Mosaic versions 2.16.4 and earlier, a universe's priority had to be statically set within the patch properties of the configuration. This priority was not changeable via a trigger and required Mosaic Designer to edit and upload the new configuration in order to modify it.  

In Mosaic 2.16.5 and above, sACN universe priority can be changed via a new trigger action 'Set sACN Universe Priority'. 

Usage

In order to use this feature you must be running Mosaic Designer 2.16.5 or higher. 

Navigate to the Trigger tab. 
Select an appropriate trigger and condition if needed. 
For the trigger's action select 'Set sACN Universe Priority'. 

This action has (4) states Set, Raise, Lower, Reset. 

Set - Allows a universes' priority to be set to a specific value.

Raise - Allows a universes' priority be raised by a set value.

Lower - Allows a universes' priority to be lowered by a set value.

Reset - Resets a universes' priority to the value specified with the patch tab of Mosaic Designer.

An example of this setup can be found below. 

Pri Switch.png
 